The concern was started in the year 2007 as a partnership entity in the name of Shree Hari Projects to undertake and execute projects on contractual basis related to water supply, storage, drainage/treatment of effluent etc. in Private and Public Sector. Owing to growing business needs it was converted into Private Limited Company in 2009 as Shree Hari Infra Projects Pvt Ltd (SHIPPL).

contact info

social networks

image
image

Ladnun Project Nagaur under Jal Jeevan Mission

“Retro-fitting Work for providing Water Supply through FHTCs in 102 villages & dhanies (other habitations) of Ladnu Block, District Nagaur by work of rising mains, Construction of New OHSRs, connecting these new OHSRs with existing and new Rising Mains, P/L/J of Pipeline from OHSRs to VTCs, Design, P/L/J and commissioning of Internal village distribution network and providing Functional House Tap water connections including all material and all labour, one year defect liability period after completion and thereafter 10 Years O & M of assets on Single point responsibility, Turnkey Lump Sum Basis under Jal Jeevan Mission (Phase -II, Package- 8, CDS – 05)”

CLIENT - PUBLIC HEALTH ENGINEERING DEPARTMENT RAJASTHAN

PROJECT COST - Rs. 112.60 Crore

Major Scope of Work

Survey and preparation of Cluster/ Village Plan Map separately.
Preparation and submission of hydraulic design of combined old and new rising main system @ 55 lpcd to deliver water to old as well as new ESRs and taking approval from department.
Replacement of 09 old pump sets with new pumps and other(if required)
Design, SLJTC  of HDPE   Cluster Distribution Main pipelines (OHSR to VTC) for 34 existing and 10 new clusters and making inter connections with existing pipeline.
Design, Construction and commissioning of 22 New OHSR.
Connecting 5 existing OHSRs of regular wing of PHED to dovetail them with the project
Inter Connecting the new OHSRs to existing rising main network/ Existing pump Houses by laying new DI rising mains
Construction of 17 New Village Transfer Chambers (VTCs)
Design, SLJTC  of HDPE Internal Village Distribution System in 68 MH and 261 OH and making inter connections with existing in-village pipeline (if any, of any type)
Providing approx. 31971 FHTCs and entering them in IMIS after collecting requisite documents.
PLC, SCADA
Miscellaneous works like NH and railway crossings, horticulture, etc.

Proposed Solution:

The primary objective of the project is to provide safe & potable drinking water to all individual households in all villages and dhanies of Ladnu through tap water connection with service level of 55 liter per capita per day. The above project was initially designed on 55 lpcd so no change in the transmission/ transfer system is required. The above project was supposed to provide water through PSPs so necessary changes are proposed in such a way so as to enable supply through FHTCs.
For supplying water with minimum 7m residual pressure, provision of new cluster ESR are kept and for new proposed ESR provision of rising mains are also kept with electromechanical works.

History:-

The  Phase II, Package-VIII (CDS-05) covered  97 Main Habitations of  Ladnu Tehsil through PSPs and CWTs but without any provision for Other Habitations. The water demand for villages was taken @ 55 lpcd. The  Water Supply Scheme   was   completed   in   year   2020.   The   existing distribution system is designed by taking peak factor as 3 and water is supplied through PSPs in main habitations only for a period of 1-2 Hours in a day while the other habitations (dhanies) are not connected with the system.
Existing FHTC Coverage & Proposed Works Presently in Ladnu Block, total 42093 FHTC are estimated for the year 2024 (Base year), out of which 10122 FHTC in 34 MH are being taken up by regular division. Therefore, remaining 31971 FHTC are proposed under this package.