The concern was started in the year 2007 as a partnership entity in the name of Shree Hari Projects to undertake and execute projects on contractual basis related to water supply, storage, drainage/treatment of effluent etc. in Private and Public Sector. Owing to growing business needs it was converted into Private Limited Company in 2009 as Shree Hari Infra Projects Pvt Ltd (SHIPPL).

contact info

social networks

image
image
image
image
image
image
image
image
image
image

DUDU-MALPURA PROJECT

Work of Regional Water Supply Scheme of 153 Village from Mor, Malpura & Pachewar Head Works on TM-1 under Bisalpur Dudu Water Supply Project on Single Responsibility Basis, i.e. Design, Build, Operation & Maintenance for 10 Years.

CLIENT  -  PUBLIC HEALTH ENGINEERING DEPARTMENT Division Malpura (RAJASTHAN)

PROJECT COST  -  79.02 Cr.

    Salient Features of the project:

    272 Kms of DI K-7 Pipeline

    961Kms of uPVC Pipeline

    4 Pump Houses- including staff quarters (complete in all respect- as per TD)

    4 Clear Water Reservoirs (Capacities between 250KL to 1000KL)

    31 Over Head Storage Reservoirs (Capacity between 100 KL to 350 KL)

    153 Village Transmission Chambers with GSM based water meters.

    1557 RCC Public Service Posts

    GSS, Four Pole structures, Transformers, Panels and other requisite electrification and instrumentation work.